EduDose
  • Home
  • GK
  • Maths
  • Reasoning
  • English
  • Computer
  • Mock Tests
  • Today’s GK
  • Menu Menu

Time and Work Exercise 1

You are here: Home1 / Maths2 / Time and Work Exercise 1
Next: Time Work Exercise 2
हिंदी वर्जन
Time limit: 0

Finish Test

0 of 25 questions completed

Questions:

  1. 1
  2. 2
  3. 3
  4. 4
  5. 5
  6. 6
  7. 7
  8. 8
  9. 9
  10. 10
  11. 11
  12. 12
  13. 13
  14. 14
  15. 15
  16. 16
  17. 17
  18. 18
  19. 19
  20. 20
  21. 21
  22. 22
  23. 23
  24. 24
  25. 25

Information

  • Most Important Multiple Choice Questions
  • Online Time and Work Exercise with Correct Answer Key and Solutions
  • Useful for all Competitive Exams

You have already completed the quiz before. Hence you can not start it again.

Test is loading...

You must sign in or sign up to start the quiz.

You have to finish following quiz, to start this quiz:

Results

0 of 25 questions answered correctly

Time has elapsed

You have reached 0 of 0 points, (0)

Categories

  1. Not categorized 0%
  1. 1
  2. 2
  3. 3
  4. 4
  5. 5
  6. 6
  7. 7
  8. 8
  9. 9
  10. 10
  11. 11
  12. 12
  13. 13
  14. 14
  15. 15
  16. 16
  17. 17
  18. 18
  19. 19
  20. 20
  21. 21
  22. 22
  23. 23
  24. 24
  25. 25
  1. Answered
  2. Review
  1. Question 1 of 25
    1. Question

    16 men can complete a piece of work in 8 days. In how many days can 12 men complete the same piece of work?

    Hint

    16 men can complete 1 work in 8 days.

    ∴ 1 man can complete 1 work in 8 × 16 days

    ∴ 12 men can complete the same work in

    time-and-work-q-64113.png= time-and-work-q-64107.png days.

  2. Question 2 of 25
    2. Question

    17 men can complete a piece of work in 12 days. In how many days can 6 men complete the same piece of work?

    Hint

    17 men can complete 1 work in 12 days

    ∴ 1 man can complete the work in 12 × 17 days

    ∴ 6 men can complete the work in

    time-and-work-q-64101.png= 34 days

  3. Question 3 of 25
    3. Question

    12 Men can complete one-third of the work in 8 days. In how many days can 16 men complete that work?

    Hint

    112 men can complete the whole work in 8 × 3 = 24 days

    ∴ Required no. of days

    time-and-work-q-64083.png

  4. Question 4 of 25
    4. Question

    Computer A takes 3 minutes to process an input while computer B takes 5 minutes. If computers A, B and C can process an average of 14 inputs in one hour, how many minutes does Computer C alone take to process one input?

    Hint

    Part processed by computer A in 1 minute =⅓

    Part processed by computer B in 1 minute =⅕

    Part processed by computer C in 1 minute

    =time-and-work-q-64077.png

    time-and-work-q-64071.png

    Hence, computer C will process 1 input 6 minutes.

  5. Question 5 of 25
    5. Question

    21 binders can bind 1400 books in 15 days. How many binders will be required to bind 800 books in 20 days?

    Hint

    Required no. of binders

    = time-and-work-q-64065.png

  6. Question 6 of 25
    6. Question

    Vikas gets Rs 350 for every day that he works. If he earns Rs 9,800 in a month of 31 days, for how many days did he work?

    Hint

    Required no. of days

    = time-and-work-q-64058.png = 28 days

  7. Question 7 of 25
    7. Question

    A man can do a piece of work in 10 days but with the assistance of his son, the work is done in 8 days. In how many days, his son alone can do the same piece of work?

    Hint

    (Man + Son)’s one day’s work = ¹⁄₈

    Man’s one day’s work =¹⁄₁₀

    ⇒ Son’s one day’s work

    = time-and-work-q-64034.png

    ∴ Son can do it in 40 days.

  8. Question 8 of 25
    8. Question

    A can knit a pair of socks in 3 days. B can knit the same thing in 6 days. If they are knitting together, in how many days will they knit two pairs of socks?

    Hint

    A’s one day’s work

    time-and-work-q-64366.png.

    B’s one day’s work

    time-and-work-q-64359.png

    (A + B)’s one day’s work

    time-and-work-q-64353.png

    ∴ A and B together can complete the work (knit a pair of socks) in 2 days.

    ∴ They together knit two pair of socks in 4 days.

  9. Question 9 of 25
    9. Question

    A group of US planes can completely destroy Bughdad in 7 days. However 12 planes develop technical faults. The remaining now can do the job in 10 days. Find the original group strength.

    Hint

    We have W = work to be done = Destruction of the city

    = X × 7 plane days, where X = original number of planes.

    Also, W = (X – 12) × 10 plane days.

    Now the work done is same in the two cases (destruction of same city)

    ⇒ X × 7 ≡ (X – 12) × 10

    ⇒ X = 40 planes.

  10. Question 10 of 25
    10. Question

    12 men take 18 days to complete a job whereas 12 women in 18 days can complete ¾ of the same job. How many days will 10 men and 8 women together take to complete the same job?

    Hint

    12 M × 18 = 12 W × 18 × ⁴⁄₃

    ∴ W = ¾M

    10M + 8W = 10M + 8 × ¾M = 16 M

    ∴ 16 men can complete the same work in

    time-and-work-q-64346.png

  11. Question 11 of 25
    11. Question

    A can do ¾ of a work in 12 days. In how many days can he finish ⅛ of the work?

    Hint

     A can do ¾ of of work in 12 days

    ∴ A can do ⅛ of the work in

    time-and-work-q-65109.png= 2 days

  12. Question 12 of 25
    12. Question

    A can finish a work in 18 days and B can do the same work in half the time taken by A. Then, working together, what part of the same work they can finish in a day?

    Hint

    A’s 1 day’s work

    = ¹⁄₁₈ and B’s 1 day’s work = ¹⁄₉

    ∴ (A + B)’s 1 day’s work

    = time-and-work-q-65102.png

  13. Question 13 of 25
    13. Question

    Bhavika alone would take 8 hours more to complete the job than when Bhavika and Ritika worked together. If Ritika worked alone, she would take 4½ hours more to complete the job than when Bhavika and Ritika worked together. What time would they take if both Bhavika and Ritika worked together?

    Hint

    Let the time taken by Bhavika and Ritika together be x days.

    ∴ Time taken by Bhavika alone

    = x + 8 days

    and time taken by Ritika alone

    = time-and-work-q-65095.png days

    ∴ 1 day’s work is

    time-and-work-q-65088.png

    ⇒ time-and-work-q-65082.png

    ⇒ time-and-work-q-65076.png

    ⇒ time-and-work-q-65070.png

    ⇒ time-and-work-q-65064.png

    ⇒ 2x² + 16x = 16x + 72

    ⇒ 2x² = 72

    ⇒ x = 6 days

  14. Question 14 of 25
    14. Question

    If 36 men can dig a trench 200 metres long, 3 meters wide and 2 metres deep in 6 days working 10 hours a day. In how many days, working 8 hours a day will 10 men dig a trench 100 metres long, 4 m wide and 3 m deep?

    Hint

    Let in x days 10 men will dig a trench

    100 m long , 4 m wide and 3m deep, working 8 hours a day

    Since, 36 men can dig a trench in 6 days in 10 hours a day

    ∴ 36 × 6 × 10 = 8 × 10 × x

    time-and-work-q-65032.png

  15. Question 15 of 25
    15. Question

    A machine P can print one lakh books in 8 hours, machine Q can print the same number of books in 10 hours while machine R can print them in 12 hours. All the machines are started at 9 a.m. while machine P is closed at 11 a.m. and the remaining two machines complete the work. Approximately at what time will the work be finished?

    Hint

    (P + Q + R)’s 1 hour’s work

    = time-and-work-q-65014.png

    Work done by P, Q and R in 2 hours

    = time-and-work-q-65007.png

    Remaining work

    = time-and-work-q-65001.png

    (Q + R)’s 1 hour’s work

    = time-and-work-q-64995.png

    Now, ¹¹⁄₆₀work is done by Q and R in 1 hour.

    So, ²³⁄₆₀ work will be done by Q and R in

    time-and-work-q-64989.pnghours ≈ 2 hours.

    So, the work will be finished approximately 2 hours after 11 a.m., i.e., around 1 p.m.

  16. Question 16 of 25
    16. Question

    10 men can complete a piece of work in 15 days and 15 women can complete the same work in 12 days. If all the 10 men and 15 women work together, in how many days will the work get completed?

    Hint

    10 men’s 1 day’s work =¹⁄₁₅;

    15 women’s 1 day’s work = ¹⁄₁₂.

    (10 men + 15 women)’s 1 day’s work

    = time-and-work-q-64983.png

    ∴ 10 men and 15 women will complete the work in

    time-and-work-q-64977.png

  17. Question 17 of 25
    17. Question

    A can do a piece of work in 10 days, while B alone can do it in 15 days. They work together for 5 days and the rest of the work is done by C in 2 days. If they get Rs 450 for the whole work, how should they divide the money?

    Hint

    Work done by A and B in 5 days

    = time-and-work-q-64971.png

    Work remaining

    = time-and-work-q-64965.png

    ∴ C alone can do the work in 6 × 2 = 12 days

    Ratio of their share work

    = time-and-work-q-64959.png

    Share of wages = Rs 225, Rs 150, Rs 75.

  18. Question 18 of 25
    18. Question

    Two men A and B working together complete a piece of work which it would have taken them 30 and 40 days respectively to complete if they worked separately. If they received a payment of Rs. 2,100, B’s share is :

    Hint

    If A and B work separately then A completes his work in 30 days and B completes his work in 40 days.

    ∴ Ratio of the days = 30: 40 = 3: 4

    ⇒ Ratio of the work of A and B = 4 : 3

    ∴ A´s share = ⁴⁄₇ and B’s share = ³⁄₇

    Now, They received Rs. 2100( together).

    ∴ B will receive a payment of

    Rs time-and-work-q-64953.png

  19. Question 19 of 25
    19. Question

    A contractor undertook to do a piece of work in 9 days. He employed certain number of laboures but 6 of them were absent from the very first day and the rest could finish the work in only 15 days. Find the number of men originally employed.

    Hint

    Let the number of men originally employed be x.

    9x = 15(x – 6)

    ⇒ x = 15

  20. Question 20 of 25
    20. Question

    X can do a piece of work in 15 days. If he is joined by Y who is 50% more efficient, in what time will X and Y together finish the work?

    Hint

    X’s one day’s work

    time-and-work-q-64947.png.

    Y’s one day’s work

    time-and-work-q-64941.png

    ∴ (x + y)’s one day’s work

    time-and-work-q-64935.png

    Hence, they together finish the work in 6 days.

  21. Question 21 of 25
    21. Question

    A can build up a wall in 8 days while B can break it in 3 days. A has worked for 4 days and then B joined to work with A for another 2 days only. In how many days will A alone build up the remaining part of wall?

    Hint

    A’s one day’s work = ⅛th work

    B’s one day’s work = ⅓rd work

    ∴ A’s 4 day’s work = 4 × ⅛ = ½ work

    ∴ In next two days, total wall

    time-and-work-q-64928.png time-and-work-q-64922.png

    Remaining wall

    time-and-work-q-64916.png

    Now, ⅛th wall is built up by A in one day.

    ∴ ¹¹⁄₁₂th wall is built up by A in

    time-and-work-q-64910.png

    = time-and-work-q-64904.png

  22. Question 22 of 25
    22. Question

    12 men complete a work in 9 days. After they have worked for 6 days, 6 more men join them. How many days will they take to complete the remaining work?

    Hint

    1 man’s 1 day’s work

    =time-and-work-q-64886.png

    12 men’s 6 day’s work

    = time-and-work-q-64880.png

    Remaining work

    = time-and-work-q-64874.png

    18 men’s 1 day’s work

    = time-and-work-q-64868.png

    ⅙ work is done by them in 1 day.

    ∴ ⅓ work is done by them in 6 × ⅓ = 2 days

  23. Question 23 of 25
    23. Question

    A can do a piece of work in 9 days and B in 18 days. They begin together, but A goes away 3 days before the work in finished. The work lasts for

    Hint

    Let work will be completed in x days.

    Then, work done by A in (x – 3) days + work done by B in x days = 1

    time-and-work-q-64862.png

    ⇒ 3x = 24

    ⇒ x = 8 days.

  24. Question 24 of 25
    24. Question

    Three men, four women and six children can complete a work in seven days. A woman does double the work a man does and a child does half the work a man does. How many women alone can complete this work in 7 days?

    Hint

    Let 1 woman’s 1 day’s work = x.

    Then, 1 man’s 1 day’s work = x/2

    and 1 child’s 1 day’s work = x/4

    So, time-and-work-q-64843.png

    ∴ 1 woman alone can complete the work in 49 days.

    So, to complete the work in 7 days, women required

    = time-and-work-q-64837.png

  25. Question 25 of 25
    25. Question

    12 men can complete a piece of work in 4 days, while 15 women can complete the same work in 4 days. 6 men start working on the job and after working for 2 days, all of them stopped working. How many women should be put on the job to complete the remaining work, If it is to be completed in 3 days?

    Hint

    1 man’s 1 day’s work = ¹⁄₄₈

    1 woman’s 1 day’s work = ¹⁄₆₀

    6 men’s 2 day’s work

    = time-and-work-q-64831.png

    Remaining work

    = time-and-work-q-64825.png

    Now, ¹⁄₆₀ work is done in 1 day by 1 woman.

    So, ¾ work will be done in 3 days by

    time-and-work-q-64819.png= 15 women.

Most Viewed Topics on EduDose
G.K.
Maths
Reasoning
English

© Copyright - edudose.com
  • Facebook
  • Twitter
  • Privacy
  • Copyright
  • Sitemap
  • About | Contact
Scroll to top